Completed works 2021

Capital developments https://capitaldevelopments.rs/zavrseni-radovi-2021/

December – finished plaster ceilings in apartments and public zones

Capital developments https://capitaldevelopments.rs/zavrseni-radovi-2021/

December – finished installation of ceramic tiles in bathrooms, sanitation assembly started

November – making layers of roof with waterproofing

Capital developments https://capitaldevelopments.rs/zavrseni-radovi-2021/

October – finished shirts in apartments

Capital developments https://capitaldevelopments.rs/zavrseni-radovi-2021/

September – installation of façade joinery completed

Capital developments https://capitaldevelopments.rs/zavrseni-radovi-2021/

September – production of underlying heating

September – plastering completed in apartments and public zones

August – installation of façade joinery

Capital developments https://capitaldevelopments.rs/zavrseni-radovi-2021/

July – completed reinforced-concrete works – construction of the building above ground part

May – making of 6th floor slab