Completed works 2020
December – completed construction of the building up to 0.00
September 2020 – Work on the production of reinforced concrete contradictions in underground floors
August – plate spill -1. Floor
July-August – completion of insurance of the foundation pit and the production of the base for waterproofing of the foundation plate
July – poles installed, excavation and insurance of the base pit
June – construction of Resavska 25